Network rail update following closure of Northampton train station

Services are being impacted further

Author: Trevor ThomasPublished 25th Nov 2024

Network Rail has issued an update to passengers following severe flooding in Northampton caused by the River Nene bursting its banks in the early hours of the morning (Monday 25th November).

Passengers are being advised that the railway through Northampton station will remain closed on Tuesday 26th November while engineers work urgently to clean up and repair flood-damaged tracks and signalling equipment.

After sustained heavy rainfall during Storm Bert, flood-water gushed through Northampton station’s platforms this morning. Vital signalling and telecoms equipment, as well as hundreds of metres of cables were submerged for hours.

The major clean-up work is expected to continue until the morning of Wednesday 27 November at the earliest.

Gary Walsh, director for Network Rail’s West Coast South route, said:

“We’re working as quickly as we can to clean up and repair damaged rail equipment after major flooding through Northampton station following Storm Bert.

“Due to the scale of damage caused to our signalling system by the flooding, we expect the railway to remain shut throughout Tuesday 26th November and urge passengers to check with National Rail Enquiries for alternative journey options. We’re really sorry to everyone affected.”

Jonny Wiseman, customer experience director for London Northwestern Railway, said:

“I am sorry for the continued disruption to journeys following the severe flooding of the railway in the Northampton area.

“I would urge all customers travelling with us on Tuesday to check their journeys before setting out as a revised timetable will be in operation, with rail replacement transport in operation on some parts of the network.”

Hear all the latest news from across the UK on the hour, every hour, on Greatest Hits Radio on DAB, smartspeaker, at greatesthitsradio.co.uk, and on the Rayo app.