Overnight sleeper 'will return to full service' in eight weeks time

From today, a key overnight train route into the West Country will only run two nights a week.

Parsons Tunnel is being extended and requires overnight line closures for work to take place
Author: Andrew KayPublished 24th Jan 2022

Overnight engineering work means the GWR Sleeper service from London to Penzance will only run two nights a week for the next eight weeks.

The Sleeper service will return on Friday 18 March between Exeter St Davids and Teignmouth after the overnight engineering works between Dawlish and Holcombe - which are part of a ÂŁ37.4m resilience project to construct a 209m rockfall shelter extension north of Parsons Tunnel.

Plymouth Sutton and Devonport MP Luke Pollard has called it the 'least worst option' as passenger numbers are still lower because of the pandemic.

But he warns it must be fully reinstated once work is finished, and not permanently changed to save costs.

A Network Rail spokesperson said: "This important work forms part of the wider South West Rail Resilience Programme which is helping protect the vital rail artery to the south west, helping to ensure a reliable train service for generations to come.

"The rockfall shelter is an extension of Parson’s Tunnel designed to protect the railway line from rocks falling from the cliff face above, which Network Rail has identified as a growing risk to the railway. While there is temporary mitigation to this problem at the moment, this work provides additional and permanent protection.

"Work on this project has recently started and engineers have identified that the condition of the ground is not sufficient to be able to safely begin the piling work from the side of the railway, and that all piling must therefore be done by a specialist piling rig from the track itself.

"During this time, GWR’s Night Riviera Sleeper service between London Paddington and Penzance will not be able to operate from Monday to Thursday evenings. The Sleeper will continue to operate as advertised on Friday and Sundays.

"The closure of the railway also means the GWR 22.02 service from Paddington to Newton Abbot via Bath and Bristol, will terminate at Exeter St Davids for the period.

"All other weekday and weekend train services are unaffected and will continue to operate as advertised."

Mike Gallop, Network Rail Western route and strategic operations director, added: “The worksite at Parsons Tunnel is in a difficult location, surrounded by sheer cliffs, the sea and a tunnel.

“While it is disappointing to need to close the railway overnight for this period, the safety of those working on the project and our passengers is paramount and we have concluded the piling for this project is most safely achieved by using a rail-mounted piling machine.

“We have seen a shift in more passengers travelling on the weekends and for leisure, so we are undertaking this work now ahead of the Easter break whilst ensuring weekend travel isn’t affected.

“I would like to thank passengers for their patience and understanding while we complete this important work that once complete, will help protect trains against falling rocks along this vital stretch of railway.”

Mark Hopwood, GWR Managing Director, said: “Our Night Riviera Sleeper service is extremely popular and provides an important link between London and Devon and Cornwall and we are sorry for the disruption that this vital engineering work will cause.

“The rockfall shelter extension is a key piece of work that in the long run will greatly improve the reliability of train services in the future. We always work with Network Rail to minimise the impact of their work on our customers. Traditionally, this might mean looking at reducing services at weekends to accommodate the extra work, however at with a reduced number of customers using this service at present due to Covid, this weekday overnight work will cause the least disruption.

“We look forward to this phase of the work being completed and restoring the world famous Night Riviera Sleeper service back to full operation.”

Anne Marie Morris, MP for Newton Abbot, commented: “I very much welcome the vital work being undertaken at Parsons Tunnel to ensure we have a resilient railway; absolutely key for local and regional connectivity and the economy.

“While it is disappointing that we will be seeing line closures to get this vital work done, I have been assured by Network Rail that every effort has been made to minimise disruption while ensuring the work can be done safely. I would ask everyone to bear with Network Rail through this disruption. In the end we will be the winners with our iconic railway line properly futureproofed.”

Plymouth Sutton and Devonport MP Luke Pollard said: "We need a fast and resilient mainline, and so I back work to get us a railway that won’t close as often at Dawlish.

"Temporarily reducing sleeper services is probably the least, worst option to achieve this.

"However, Ministers must not use this as a precedent for cuts, as we know they’re trying to cut rail funding by 10%. The Sleeper service, alongside other routes in the South West, must not be cut."

Hear all the latest news from across the UK on the hour, every hour, on Greatest Hits Radio on DAB, smartspeaker, at greatesthitsradio.co.uk, and on the Rayo app.